Good evening to anyone. I’m trying desperately to fit this table into an horizontal page. As I’ve used excel2latex to import it, I’m using the array environment, and I don’t really know what to do to make it fit… I tried to use tabularx, but I LaTeX cannot compile… The table seems too large and too tall…

documentclass{article}
usepackage[utf8]{inputenc}
linespread{1.3}
usepackage[margin=1.2in]{geometry}
usepackage{eurosym}
usepackage{makeidx}
usepackage{amsfonts}
usepackage{amssymb}
usepackage{graphicx}
usepackage{amsmath}
usepackage{cases}
usepackage[titletoc]{appendix}
usepackage{color,soul}
usepackage{amsthm}
usepackage{thmtools}
usepackage{mathrsfs}
usepackage{enumerate}
usepackage{hyperref}
usepackage[hyphens]{url}
usepackage{pgfplots}
usetikzlibrary{patterns}
usepgfplotslibrary{groupplots}
usepackage{lscape}
usepackage{caption}
usepackage{subfigure}
usepackage{tabularx}

begin{document}
begin{landscape}
begin{array}{l l l l l l l l l l l l}

      &   &   &   &   &   &   &   &   &   &   &   
    Economic Analysis & Unit of Measure & BAU &  &  &  & textbf{PROJECT} &  &  &  &  &   hline
     &  & 2024-2029**  &  & 2030-2041  &  & 2024-2025 &  & 2026-2029**  &  & 2030-2041  &   hline
     &  & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak  
    Investment & € & 0 &  & 0 &  & 175 &  & 0 &  & 0 &   hline
    VOT  & €/h & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10  hline
    Extra Delay  & h & 0.67 & 0.33 & 0.67 & 0.33 & 0.67 & 0.33 & 0.33 & 0.17 & 0.33 & 0.17  hline
    Delay costs & € & 6.67 & 3.33 & 6.67 & 3.33 & 6.67 & 3.33 & 3.33 & 1.67 & 3.33 & 1.67  hline
    A&D Tourist & mln / year & 8 & 2 & 5.5 & 1.17 & 8 & 2 & 8.33 & 2.06 & 5.83 & 1.22  hline
    A&D Locals  & mln / year & 2 & 3 & 1.875 & 2.75 & 2 & 3 & 2.07 & 3.07 & 1.89 & 2.77  hline
    TOTAL & mln / year & 10 & 5 & 7.36 & 3.92 & 10 & 5 & 10.4 & 5.12 & 7.72 & 3.99  hline
    Price Tourist & €/trip & 160 & 120 & 185 & 145 & 160 & 120 & 160 & 120 & 185 & 145  hline
    Elasticity (Tourist) &  & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2  hline
    Res. Price (Tourist)  & €/trip & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180  hline
    Price Locals & €/trip & 40 & 30 & 65 & 55 & 40 & 30 & 40 & 30 & 65 & 55  hline
    Elasticity (Locals)  &  & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4  hline
    Res. Price (Locals)  & €/trip & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420  hline
    Subsidy (€/trip)  & €/trip & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90  hline
    Revenues (Tourist)  & mln € & 1280 & 240 & 880 & 140 & 1280 & 240 & 1333.33 & 246.67 & 933.33 & 146.67  hline
    Revenues (Locals) & mln € & 80 & 90 & 75 & 82.5 & 80 & 90 & 82.67 & 92 & 75.67 & 83  hline
    TOTAL REVENUES & mln € & 1690 &  & 1177.5 &  & 1690 &  & 1754.67 &  & 1238.67 &   hline
    CS (Tourist)  & mln € & 320 & 60 & 151.25 & 20.42 & 320 & 60 & 347.22 & 63.38 & 170.14 & 22.41  hline
    CS (Locals)  & mln € & 640 & 720 & 576.5625 & 625.625 & 640 & 720 & 664.78 & 738.56 & 584.84 & 631.72  hline
    TOTAL CS & mln € & 1740 &  & 1373.85 &  & 1740 &  & 1813.94 &  & 1409.11 &   hline
    GROSS WELFARE  & mln € & 3430 &  & 2551.35 &  & 3430 &  & 3568.6 &  & 2647.76 &   hline
    Permits 2030  & (€ / ton CO2 pas trip) & 50 &  &  &  & 50 &  &  &  & 50 &   hline
    Social Discount Rate &  & 0.05 &  &  &  & 0.05 &  &  &  & 0.05 &   hline
    Actual Permit Prices & / ton CO2 pas trip) & 37.31 &  &  &  & 37.31 &  &  &  & 37.31 &   hline
    Emissions & text{ton $CO_2$ / pas trip} & 0.5 &  &  &  & 0.5 &  &  &  & 0.5 &   hline
    TOTAL EXTERNAL COSTS* & (€) (year) & 279.83 &  & 0 &  & 279.83 &  & 289.57 &  & 0 &   hline
    FLOW EXTERNAL COSTS* & (€) & 1678.98 &  & 0 &  & 559.66 &  & 1158.29 &  & 0 &   hline
    NPV & (€) & 31544.88 &  &  &  & 32223.96 &  &  &  &  &   hline
     &  &  &  &  &   &   &   &   &   &   &    hline
    NET BENEFIT &  &  & 679.072 &  &  &  &  &  &  &   &    hline
     &  &  &  &  &  &  &  &  &  &  &    hline
    IRR &  &  & 0.29 & #NUM! &  &  &  &  &  &  &    hline
end{array}
end{landscape}


end{document}

Overfull hbox (307.39384pt too wide) in paragraph at lines 154--193
Overfull vbox (129.3531pt too high) has occurred while output is active []

3 Answers

Here's a solution that employs a tabular environment (actually, a tabular* environment) instead of an array environment, embeds the tabular material in a sidewaystable environment, takes some care to structure the header material, and uses few but well-spaced horizontal rules. No need to reduce the font size.

enter image description here

documentclass{article}
usepackage[utf8]{inputenc}
%linespread{1.3} % don't use the low-level macro 'linespread' directly
usepackage{setspace}setstretch{1.3}
usepackage[margin=1.2in]{geometry}
usepackage{eurosym}
usepackage{makeidx}
%%usepackage{amsfonts} % is loaded automatically by 'amssymb'
usepackage{amssymb}
usepackage{graphicx}
usepackage{amsmath}
usepackage{cases}
usepackage[titletoc]{appendix}
usepackage{color,soul}
usepackage{amsthm}
usepackage{thmtools}
usepackage{mathrsfs}
usepackage{enumerate} % 'enumitem' package would be a better choice
usepackage{pgfplots}
usetikzlibrary{patterns}
usepgfplotslibrary{groupplots}
%%usepackage{lscape}
usepackage{pdflscape}
usepackage{caption}
%%usepackage{subfigure} % 'subfigure' is deprecated! 
usepackage{subcaption}
usepackage{tabularx}
usepackage{booktabs,mhchem,rotating} % <-- new
%%usepackage[hyphens]{url}
usepackage{xurl}
usepackage{hyperref} % load this package _last_

begin{document}

begin{sidewaystable}
setlengthtabcolsep{0pt}
begin{tabular*}{textwidth}{@{extracolsep{fill}} *{12}{l} }
    toprule
    Economic variable & Unit & multicolumn{4}{c}{BAU} & multicolumn{6}{c}{PROJECT}  
    cmidrule{3-6} cmidrule{7-12}
     & &  multicolumn{2}{c}{2024--2029**} & 
          multicolumn{2}{c}{2030--2041}   & 
          multicolumn{2}{c}{2024--2025}   & 
          multicolumn{2}{c}{2026--2029**} &  
          multicolumn{2}{c}{2030--2041}    
    cmidrule{3-4} cmidrule{5-6} cmidrule{7-8} cmidrule{9-10} cmidrule{11-12}
    & &  Peak & O/P & Peak & O/P & Peak & O/P & Peak & O/P & Peak & O/P  
    midrule
    Investment   & €        & 0 & & 0 & & 175 & & 0 & & 0 &   
    VOT          & €/h      & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10  
    Extra Delay  & h        & 0.67 & 0.33 & 0.67 & 0.33 & 0.67 & 0.33 & 0.33 & 0.17 & 0.33 & 0.17  
    Delay costs  & €        & 6.67 & 3.33 & 6.67 & 3.33 & 6.67 & 3.33 & 3.33 & 1.67 & 3.33 & 1.67  
    A&D Tourist & mln/year & 8 & 2 & 5.5 & 1.17 & 8 & 2 & 8.33 & 2.06 & 5.83 & 1.22  
    A&D Locals  & mln/year & 2 & 3 & 1.875 & 2.75 & 2 & 3 & 2.07 & 3.07 & 1.89 & 2.77  
    TOTAL        & mln/year & 10 & 5 & 7.36 & 3.92 & 10 & 5 & 10.4 & 5.12 & 7.72 & 3.99  
    Price Tourist& €/trip   & 160 & 120 & 185 & 145 & 160 & 120 & 160 & 120 & 185 & 145  
    Elasticity (Tourist) & -- & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2  
    Res. Price (Tourist)  & €/trip & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180  
    Price Locals & €/trip & 40 & 30 & 65 & 55 & 40 & 30 & 40 & 30 & 65 & 55  
    Elasticity (Locals)  & -- & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4  
    Res. Price (Locals)  & €/trip & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420  
    Subsidy (€/trip)  & €/trip & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90  
    Revenues (Tourist)  & mln € & 1280 & 240 & 880 & 140 & 1280 & 240 & 1333.33 & 246.67 & 933.33 & 146.67  
    Revenues (Locals) & mln € & 80 & 90 & 75 & 82.5 & 80 & 90 & 82.67 & 92 & 75.67 & 83  
    TOTAL REVENUES & mln € & 1690 & & 1177.5 & & 1690 & & 1754.67 & & 1238.67 &   
    CS (Tourist)   & mln € & 320 & 60 & 151.25 & 20.42 & 320 & 60 & 347.22 & 63.38 & 170.14 & 22.41  
    CS (Locals)    & mln € & 640 & 720 & 576.5625 & 625.625 & 640 & 720 & 664.78 & 738.56 & 584.84 & 631.72  
    TOTAL CS       & mln € & 1740 & & 1373.85 & & 1740 & & 1813.94 & & 1409.11 &   
    GROSS WELFARE  & mln € & 3430 & & 2551.35 & & 3430 & & 3568.6 & & 2647.76 &   
    Permits 2030   & €/ton ce{CO2} pas trip & 50 & &  & & 50 & &  & & 50 &   
    Social Discount Rate & & 0.05 & &  & & 0.05 & &  & & 0.05 &   
    Actual Permit Prices &/ton ce{CO2} pas trip & 37.31 & &  & & 37.31 & &  & & 37.31 &   
    Emissions      & ton ce{CO2}/pas trip & 0.5 & &  & & 0.5 & &  & & 0.5 &   
    addlinespace
    TOTAL EXT. COSTS* & € (year) & 279.83 & & 0 & & 279.83 & & 289.57 & & 0 &   
    FLOW EXT. COSTS* & € & 1678.98 & & 0 & & 559.66 & & 1158.29 & & 0 &   
    NPV & € & 31544.88 & &  & & 32223.96    
    NET BENEFIT & &  & 679.072  
    IRR & &  & 0.29 & #NUM!   
    bottomrule
end{tabular*}
end{sidewaystable}

end{document}

Correct answer by Mico on January 20, 2021

You were using the array environment outside math mode. Also, there was a conflict concerning the url package. I have also reduced the font size. This will work:

documentclass{article}
usepackage[utf8]{inputenc}
linespread{1.3}
usepackage[margin=1.2in]{geometry}
usepackage{eurosym}
usepackage{makeidx}
usepackage{amsfonts}
usepackage{amssymb}
usepackage{graphicx}
usepackage{amsmath}
usepackage{cases}
usepackage[titletoc]{appendix}
usepackage{color,soul}
usepackage{amsthm}
usepackage{thmtools}
usepackage{mathrsfs}
usepackage{enumerate}
usepackage{hyperref}
usepackage{pgfplots}
usetikzlibrary{patterns}
usepgfplotslibrary{groupplots}
usepackage{lscape}
usepackage{caption}
usepackage{subfigure}
usepackage{tabularx}

begin{document}
begin{landscape}tiny
begin{tabular}{l l l l l l l l l l l l}

      &   &   &   &   &   &   &   &   &   &   &   
    Economic Analysis & Unit of Measure & BAU &  &  &  & textbf{PROJECT} &  &  &  &  &   hline
     &  & 2024-2029**  &  & 2030-2041  &  & 2024-2025 &  & 2026-2029**  &  & 2030-2041  &   hline
     &  & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak  
    Investment & € & 0 &  & 0 &  & 175 &  & 0 &  & 0 &   hline
    VOT  & €/h & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10  hline
    Extra Delay  & h & 0.67 & 0.33 & 0.67 & 0.33 & 0.67 & 0.33 & 0.33 & 0.17 & 0.33 & 0.17  hline
    Delay costs & € & 6.67 & 3.33 & 6.67 & 3.33 & 6.67 & 3.33 & 3.33 & 1.67 & 3.33 & 1.67  hline
    A&D Tourist & mln / year & 8 & 2 & 5.5 & 1.17 & 8 & 2 & 8.33 & 2.06 & 5.83 & 1.22  hline
    A&D Locals  & mln / year & 2 & 3 & 1.875 & 2.75 & 2 & 3 & 2.07 & 3.07 & 1.89 & 2.77  hline
    TOTAL & mln / year & 10 & 5 & 7.36 & 3.92 & 10 & 5 & 10.4 & 5.12 & 7.72 & 3.99  hline
    Price Tourist & €/trip & 160 & 120 & 185 & 145 & 160 & 120 & 160 & 120 & 185 & 145  hline
    Elasticity (Tourist) &  & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2  hline
    Res. Price (Tourist)  & €/trip & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180  hline
    Price Locals & €/trip & 40 & 30 & 65 & 55 & 40 & 30 & 40 & 30 & 65 & 55  hline
    Elasticity (Locals)  &  & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4  hline
    Res. Price (Locals)  & €/trip & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420  hline
    Subsidy (€/trip)  & €/trip & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90  hline
    Revenues (Tourist)  & mln € & 1280 & 240 & 880 & 140 & 1280 & 240 & 1333.33 & 246.67 & 933.33 & 146.67  hline
    Revenues (Locals) & mln € & 80 & 90 & 75 & 82.5 & 80 & 90 & 82.67 & 92 & 75.67 & 83  hline
    TOTAL REVENUES & mln € & 1690 &  & 1177.5 &  & 1690 &  & 1754.67 &  & 1238.67 &   hline
    CS (Tourist)  & mln € & 320 & 60 & 151.25 & 20.42 & 320 & 60 & 347.22 & 63.38 & 170.14 & 22.41  hline
    CS (Locals)  & mln € & 640 & 720 & 576.5625 & 625.625 & 640 & 720 & 664.78 & 738.56 & 584.84 & 631.72  hline
    TOTAL CS & mln € & 1740 &  & 1373.85 &  & 1740 &  & 1813.94 &  & 1409.11 &   hline
    GROSS WELFARE  & mln € & 3430 &  & 2551.35 &  & 3430 &  & 3568.6 &  & 2647.76 &   hline
    Permits 2030  & (€ / ton CO2 pas trip) & 50 &  &  &  & 50 &  &  &  & 50 &   hline
    Social Discount Rate &  & 0.05 &  &  &  & 0.05 &  &  &  & 0.05 &   hline
    Actual Permit Prices & / ton CO2 pas trip) & 37.31 &  &  &  & 37.31 &  &  &  & 37.31 &   hline
    Emissions & text{ton $CO_2$ / pas trip} & 0.5 &  &  &  & 0.5 &  &  &  & 0.5 &   hline
    TOTAL EXTERNAL COSTS* & (€) (year) & 279.83 &  & 0 &  & 279.83 &  & 289.57 &  & 0 &   hline
    FLOW EXTERNAL COSTS* & (€) & 1678.98 &  & 0 &  & 559.66 &  & 1158.29 &  & 0 &   hline
    NPV & (€) & 31544.88 &  &  &  & 32223.96 &  &  &  &  &   hline
     &  &  &  &  &   &   &   &   &   &   &    hline
    NET BENEFIT &  &  & 679.072 &  &  &  &  &  &  &   &    hline
     &  &  &  &  &  &  &  &  &  &  &    hline
    IRR &  &  & 0.29 & #NUM! &  &  &  &  &  &  &    hline
end{tabular}
end{landscape}


end{document}

Answered by José Carlos Santos on January 20, 2021

First I added booktabs, always useful for better row spacing and rules, and pdflscape to be able to see the landscape table horizontally in the monitor, for easier debugging. The font size is small, the rows stretched by arraystretch from the array package. I added some multicolumns to center the second row over Peak / Off-Peack and centered most columns for better viewing.

enter image description here

documentclass{article}
usepackage[utf8]{inputenc}
%linespread{1.3}
usepackage[margin=1.2cm]{geometry}
usepackage{eurosym}
usepackage{makeidx}
usepackage{amsfonts}
usepackage{amssymb}
usepackage{graphicx}
usepackage{amsmath}
usepackage{cases}
usepackage[titletoc]{appendix}
usepackage{color,soul}
usepackage{amsthm}
usepackage{thmtools}
usepackage{mathrsfs}
usepackage{enumerate}
usepackage{hyperref}
usepackage{pgfplots}
usetikzlibrary{patterns}
usepgfplotslibrary{groupplots}
usepackage{lscape}
usepackage{caption}
usepackage{subfigure}
usepackage{tabularx}

RequirePackage{pdflscape} % added  
RequirePackage{booktabs} % added

begin{document}
begin{landscape}
    small
renewcommand{arraystretch}{1.3} %% added  
    
begin{tabular}{l c c c c c c c c c c c}

%      &   &   &   &   &   &   &   &   &   &   &   
toprule
    Economic Analysis & Unit of Measure  BAU &multicolumn{10}{c}{textbf{PROJECT}}  
    toprule
     &  & multicolumn{2}{c}{2024-2029**}   & multicolumn{2}{c}{2030-2041 } & multicolumn{2}{c}{2024-2025} & multicolumn{2}{c}{2026-2029**}  & multicolumn{2}{c}{2030-2041}  hline      
     &  & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak & Peak & Off-Peak  midrule
    Investment & € & 0 &  & 0 &  & 175 &  & 0 &  & 0 &   hline
    VOT  & €/h & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10 & 10  hline
    Extra Delay  & h & 0.67 & 0.33 & 0.67 & 0.33 & 0.67 & 0.33 & 0.33 & 0.17 & 0.33 & 0.17  hline
    Delay costs & € & 6.67 & 3.33 & 6.67 & 3.33 & 6.67 & 3.33 & 3.33 & 1.67 & 3.33 & 1.67  hline
    A&D Tourist & mln / year & 8 & 2 & 5.5 & 1.17 & 8 & 2 & 8.33 & 2.06 & 5.83 & 1.22  hline
    A&D Locals  & mln / year & 2 & 3 & 1.875 & 2.75 & 2 & 3 & 2.07 & 3.07 & 1.89 & 2.77  hline
    TOTAL & mln / year & 10 & 5 & 7.36 & 3.92 & 10 & 5 & 10.4 & 5.12 & 7.72 & 3.99  hline
    Price Tourist & €/trip & 160 & 120 & 185 & 145 & 160 & 120 & 160 & 120 & 185 & 145  hline
    Elasticity (Tourist) &  & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2 & 2  hline
    Res. Price (Tourist)  & €/trip & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180 & 240 & 180  hline
    Price Locals & €/trip & 40 & 30 & 65 & 55 & 40 & 30 & 40 & 30 & 65 & 55  hline
    Elasticity (Locals)  &  & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4 & 0.4  hline
    Res. Price (Locals)  & €/trip & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420 & 560 & 420  hline
    Subsidy (€/trip)  & €/trip & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90 & 120 & 90  hline
    Revenues (Tourist)  & mln € & 1280 & 240 & 880 & 140 & 1280 & 240 & 1333.33 & 246.67 & 933.33 & 146.67  hline
    Revenues (Locals) & mln € & 80 & 90 & 75 & 82.5 & 80 & 90 & 82.67 & 92 & 75.67 & 83  hline
    TOTAL REVENUES & mln € & 1690 &  & 1177.5 &  & 1690 &  & 1754.67 &  & 1238.67 &   hline
    CS (Tourist)  & mln € & 320 & 60 & 151.25 & 20.42 & 320 & 60 & 347.22 & 63.38 & 170.14 & 22.41  hline
    CS (Locals)  & mln € & 640 & 720 & 576.5625 & 625.625 & 640 & 720 & 664.78 & 738.56 & 584.84 & 631.72  hline
    TOTAL CS & mln € & 1740 &  & 1373.85 &  & 1740 &  & 1813.94 &  & 1409.11 &   hline
    GROSS WELFARE  & mln € & 3430 &  & 2551.35 &  & 3430 &  & 3568.6 &  & 2647.76 &   hline
    Permits 2030  & (€ / ton CO2 pas trip) & 50 &  &  &  & 50 &  &  &  & 50 &   hline
    Social Discount Rate &  & 0.05 &  &  &  & 0.05 &  &  &  & 0.05 &   hline
    Actual Permit Prices & / ton CO2 pas trip) & 37.31 &  &  &  & 37.31 &  &  &  & 37.31 &   hline
    Emissions & text{ton $CO_2$ / pas trip} & 0.5 &  &  &  & 0.5 &  &  &  & 0.5 &   hline
    TOTAL EXTERNAL COSTS* & (€) (year) & 279.83 &  & 0 &  & 279.83 &  & 289.57 &  & 0 &   hline
    FLOW EXTERNAL COSTS* & (€) & 1678.98 &  & 0 &  & 559.66 &  & 1158.29 &  & 0 &   hline
    NPV & (€) & 31544.88 &  &  &  & 32223.96 &  &  &  &  &   hline
     &  &  &  &  &   &   &   &   &   &   &    hline
    NET BENEFIT &  &  & 679.072 &  &  &  &  &  &  &   &    hline
     &  &  &  &  &  &  &  &  &  &  &    hline
    IRR &  &  & 0.29 & #NUM! &  &  &  &  &  &  &  bottomrule
end{tabular}
end{landscape}


end{document}

Answered by Simon Dispa on January 20, 2021